English 中文
The installation of the cone crusher frame:We should keep the strict verticality and horizontality when install the frame, and we can use the gradienter or netsuke to check the median of the pedestal on the ring processing surface of the pedestal; After adjust the level of the pedestal using the adjusting wedge, tighten up the cone crusher foundation screw , and we can go with the second grouting; After the second grouting, take the adjusting wedge from the cone crusher pedestal, then fill the void with the cement, then check the installation of the frame according to the above; Keep the verticality and horizontality of the pedestal, ensure the cone crusher can work faithfully, or else the copper sheathing get in touch with each together, will abrade the eccentric bushing, the sealing device will not work normally.
The installation of the transmission shaft of the cone crusher; Put the adjusting wedge between the flange that between the pedestal and the frame of the transmission shaft when install the transmission shaft; After the installation of the transmission shaft, check the size of the transmitting gear with the sample plate; The amount of the movement of the transmitting gear should be 0.4-0.6mm; When disassemble the cone crusher transmission shaft, you can use the flange, but if you will not disassemble the transmission shaft, please keep the screw out of the shaft..